en:robotina_charger:commissioning:pv_inverter [2022/12/09 13:57] – [EVSE and PV inverter connection] gdzampoen:robotina_charger:commissioning:pv_inverter [2022/12/09 14:59] (current) – [EVSE and PV inverter connection] gdzampo
Line 25: Line 25:
 To add inverter on HEMS configurator: To add inverter on HEMS configurator:
   *   on settings page inside source table, select SolarEdge inverter. Please see [[en:robotina_charger:software#settings|]]   *   on settings page inside source table, select SolarEdge inverter. Please see [[en:robotina_charger:software#settings|]]
-  *   on io mux page define IP address for inverter. Please see [[en:robotina_charger:software#io mux|]] +  *   on io mux page set IP address for inverter. Please see [[en:robotina_charger:software#io_mux|]] 
  
 To setup Modbus TCP on Inverter using SetApp: To setup Modbus TCP on Inverter using SetApp:
   *   Select Site Communication menu    *   Select Site Communication menu 
      * RS485-1 -> Protocol -> SunSpec (Non-SE Logger)      * RS485-1 -> Protocol -> SunSpec (Non-SE Logger)
-     * RS485-1 -> Device ID, and enter the number 1. +     * RS485-1 -> Device ID, and enter the number 1 
-     Select Modbus TCP and set to Enable. +     * Modbus TCP and set to Enable 
-     To modify the *TCP port, select Port, set the port number to 502+     set TCP port to 502
-     +
  
- +**Note**:\\ The TCP server idle time is 2 minutes. In order to leave the connection open, the request should be made within 2 minutes.\\ It is important to follow rules above, firstly to set HEMS configurator following Inverter setup due to 2 minutes time frame.
-*TCP port is 1502 by default.+
en/robotina_charger/commissioning/pv_inverter.1670594226.txt.gz · Last modified: 2022/12/09 13:57 by gdzampo