en:robotina_charger:commissioning:pv_inverter
This is an old revision of the document!
Power plant connection
The power plants can be connected to the grid in two ways:
When configuring the power plant, select
- in: serial (internal) with grid power sensor
- ex: parallel (external) with grid power sensor
The power plants are configured as internal by default.
PV inverter
Monitoring of PV Inverter is possible by two ways:
1. adding of power-sensor to measure produced electricity. How to add power sensor please see Power Sensor
2. connecting PV inverter by Modbus TCP to EVSE (only for SolarEdge inverters)
One-phase sensor PM1-E-D
- Connect communication bus (to only one power-sensor)
- In HEMS Configurator power-sensor should appear as a “new device”
- Press and hold the push-button on the power-sensor until it appears -SEt- on display
- In HEMS Configurator click on the “ add” button next to the source or consumer that the sensor is measuring
- Connect communication bus to the next power-sensor and repeat procedure