Commissioning

Control system

HEMS controller HC-IQ-HEMS and all communication interfaces are supplied with preinstalled firmware.

For system configuration use HIQ HEMS Configurator .

Power meters

  1. Connect only one new power meter at the time.
  2. In HIQ HEMS Configurator go to settings page. New power-meter should be detected (Address and Type should be displayed).
  3. Long-press button on power meter until -SET- is displayed.
  4. Press New address and enter new address according to following table.
Device Address
Grid 150
1st power plant 154
2nd power plant 155
3rd power plant 156
1st storage 157
2nd storage 158
1st consumer 160
2nd consumer 161
8th consumer 167

Load managers

Add new device

  1. In HIQ HEMS Configurator go to wireless page
  2. Click on device which will be added
  3. Wait for network open - waiting device status.
  4. Press button on device.
  5. Wait until device is addressed and configured.

Procedure can be interrupted with “close network” button.

Remove device

  1. Reset device:
    • power off wireless device for a few seconds.
    • After powering on wait for a few seconds for device to boot on.
    • Press and hold button, LED indicator will go off, then green and at the end red.
    • Release button.
  2. In HIQ HEMS Configurator go to wireless page
  3. Reset device should have error state (yellow sign with exclamation)
  4. Click on reset device to clear place.

Control devices

  1. In HIQ HEMS Configurator go to wireless page
  2. Press icon for control device (wireless enocean push-button) to be configured
  3. On control device press 0 (off) button
  4. On control device press 1 (on) button

Sensors

Add new sensor

  1. Adjust sensor address with DIP-switches according following table
  2. In HIQ HEMS Configurator click on sensor which will be added
  3. Wait for network open - waiting device status
  4. Power on and pres button on sensor
  5. Wait until sensor is configured

Procedure can be interrupted with “close network” button.

Sensor Address DIP switch settings
S1 60
S2 61
S3 62
S4 63
S5 64
S6 65
S7 66
S8 67

Remove sensor

  1. Reset sensor:
    • Power off sensor for few seconds
    • Reconnect sensor power supply
    • After sensor power on (but within 20 sec) press and hold button for at least 6 sec
  2. In HIQ HEMS Configurator reset device should show error
  3. Click on error icon to free occupied space
en/goflex_hems/methods_resources/commissioning.txt · Last modified: 2019/08/14 10:49 by goran.kocjancic